THE BUILDING CODES & SERVICES OFFICE WILL MAKE
INSPECTIONS AT THE FOLLOWING STAGES PROGRESS:
|
|
- Footings (before any concrete is poured)
- Plumbing, mechanical and electrical under slab (before being covered
up)
- Slab (before any concrete is poured)
- Foundation (when the floor system is started, but before any sub-flooring
placement)
- Rebar/Reinforcement (if required, when rebar is in place, before pouring
concrete)
- Chimney inspection (when firebox and throat are in place, and beginning
with the flue liner)
- Stucco *(must be inspected before stucco material is to be installed)
- Rough-in inspection (framing, electrical, plumbing,
mechanical)
- Rough-in outside only (house wrap, flashing, etc.)
- Insulation
- Water and/or sewer yard lines
- Final inspection
|
|